Commissioners Discuss Proposed Addition to Hardin Hills at Recent Meeting

Written on April 1, 2021

Hardin Hills Administrator Sharon Huston, along with pH7 Architects, met the Hardin County Commissioners on Zoom at a recent meeting to discuss a proposed addition to Hardin Hills.  

Scott Deisler and Mike Healy presented an initial assessment to add 9 private rooms and 9 restrooms with showers and a physical therapy room for a total of 5700 square feet. 

An estimate of probable cost is $1.9 million dollars.

This is an early opinion of construction cost with no soft cost included, which would include furniture; equipment, etc. 

They anticipate 3-4 months for the design, one month advertising and one month procurement and 9-10 months of construction. 

The Commissioners will review the option as well as other options and funding.