The Ada Police Department released an update on the municipal building renovation project.  

Electrical work is well on its way and the HVAC has been installed.

Contractors are now in the process of placing dry wall while they wait for delivery of the elevator. 

 

Windows have been installed along the west wall of the police department.

Along with this project, village council opted to install a generator powerful enough to run the entire municipal building in cases of electrical outages. The pad for the generator has been installed as well as the protecting barriers.

The $700,000 project is slightly behind schedule, however, it is estimated to be near the half-way point.