News

Abatement of B and C Buildings at KHS Complete, Underway at Old KMS; Demolition to Follow

todayMarch 6, 2026 1341 5

share close

The process to raze the old Kenton Middle School and the B and C Buildings of the Kenton High School is underway.

The abatement of B & C Buildings is complete and went well.

The construction team is working on disconnecting utilities, and they expect heavy equipment to move in starting next week, and demolition to begin shortly thereafter.

At KMS, abatement is underway and will continue into April.

If all goes according to plan there, heavy equipment will begin showing up around Easter.